Woodford Leisure Centre

A refurbished and extended leisure centre, delivered on time and within budget

Location: Hull
Sector: Leisure and community
Contract value: Approximately £9.2m
Shard Stone's role: Cost consultant

The refurbishment and extension of an operational leisure centre, where the scope expanded during the works to include replacement roofing and rooflights,  increasing the contract value by over £1 million.

What Shard Stone Delivered

Shard Stone’s financial management and commercial oversight ran throughout, so the client could manage spending against its approved funding as the roofing works were added.

The Outcome

Delivered on time and within budget after around 18 months on site, with the additional roofing works incorporated into the original programme.

A reliable cost position isn’t set once. It’s maintained as the project changes.